The Long Thanh airport timeline came under review on Nov. 25 after the Airports Corporation of Vietnam said key first-phase work would run into 2027. Vietnam News reported that the developer proposed extending the overall implementation period for that phase into 2027–28.

Deputy Prime Minister Phạm Gia Túc asked ministries, local authorities and the developer to resolve outstanding issues and ensure the airport meets safety requirements. Several packages, including the passenger terminal and the first cargo terminal, are now expected to finish construction or trial operations in June 2027. An official revised opening date remains pending.



What is driving the Long Thanh airport timeline

The developer told the government review that its main construction component could not finish in full during 2026 as planned. That part of the project includes the terminal and other systems needed to move passengers, baggage and aircraft through the airport.

In its account of the Long Thanh airport timeline, Vietnam News also identified the airport management system and parking facilities among the packages expected to reach completion or finish trials in June 2027. These milestones cover different stages of readiness. A finished building may still need its systems tested before airport staff can use it in routine service.


Why completion and passenger service have separate dates

The government review stressed that Long Thành needs project acceptance, an operational assessment and the relevant aviation licenses before it can open. Those steps depend on how the facilities work together. A completed structure by itself does not resolve outstanding work on access, equipment or air traffic systems.

Vietnam News also reported that Vietnam Airlines asked for adequate preparation time because international customers often make bookings months in advance. Airlines need an operating date to schedule aircraft and crews and to explain which airport will handle a booking. Those details become important once transfers or changes to existing routes are planned.


What the new airport is supposed to change

Long Thành is being built in Đồng Nai Province to serve the wider Ho Chi Minh City region. The project is intended to ease pressure on Tân Sơn Nhất International Airport. Opening the new site therefore involves both certifying its facilities and coordinating how airlines and passengers use the two airports.

Authorities in Ho Chi Minh City and Đồng Nai reported work on traffic arrangements and connections. Those projects will influence how passengers reach the airport once services begin. As officials review the Long Thanh airport timeline, the government has asked the developer to work out when operational information can be released so airlines can prepare.

Related coverage from The Aviation Diary includes United Airlines’ terminal opening in Houston.


FAQ: Long Thanh airport timeline

What changed in the Long Thanh airport timeline?

The developer told the government that its main construction component would miss the 2026 deadline and proposed extending the project’s first-phase implementation period.

When could the passenger terminal be ready?

The passenger terminal is among the packages expected to finish construction or trials in June 2027, according to reporting on the government review.

When will Long Thành open to regular passengers?

An official revised opening date remains pending. Acceptance, operational assessments and licensing must take place before the airport can open.


Looking Ahead

The Ministry of Construction was asked to submit a progress report before Dec. 10. That review is the next opportunity to see how officials will handle the proposed extension and set the sequence for testing and licensing.


Sources

Feature photo by Stevetruong (CC BY-SA 4.0).

Nabeel Khan

Written by

Nabeel Khan

Nabeel Khan is the founder and editor of The Aviation Diary. A mechanical engineer working in the aerospace industry, he covers military and commercial aviation, defense, and space. Views expressed are his own.

More from this author →